Adaptive Agile in Action – A Case Study

 

Adaptive Agile in Action – A Case Study


Expectations from Team:

  • Very basic of Agile is to have development at fast pace
  • Handle the 6 months Project road-map in smaller 14 days sprints
  • Adapt to frequently changing client requirements
  • Client and Project Teams work closer than in any other Project Management Model
    Challenges we had in project:
    • Requirements were changing on daily basis and this could have affected the whole product so we decided to go for adaptive agile method
    • End date to deliver the project was fixed
    • Customer wanted to be a part of the Project closely
    • Delivering lots of content with in fixed deadline was a challenge
      How we handled those challenges:

      • Daily SCRUM meetings, Project Road map broken down into Mini Projects or Sprints
      • Framework per Sprint ensuring each Sprint should have appropriate “User Stories”
      • Client, Product Owner and BA worked closely through meetings, walkthroughs, midpoints and progress reports

      Everyone to follow the Daily Stand-up rule of answering three questions:
      • What I accomplished yesterday?
      • What I will be accomplishing today?
      • Any Impediments
      (Ground Rule: Daily SCRUM to be wrapped up within 15 minutes)
      Key Learning
      • Agile gives you the ready work product at the end of every sprint…Client can share the findings and recommendations at any time once a sprint is over and move towards the “BIG PICTURE” of completing the Project Road-map
      • It gets easier to Ready to accommodate changes if the Project Teams follows the “Adaptive Agile Methodology”